A Quick Turn Around

When Hemisphere were contacted at the 11th hour by a new client whose shipment was already underway, our project managers quickly stepped in and were able to assess the client’s requirements and find a suitable solution.


Unfortunately, the client had been let down when another party were no longer able to offer a workable solution. Within hours, we presented a tailor-made and fully comprehensive transport solution, which not only met the shipper and consignee’s needs, but was also substantially under our client’s initial budget for the shipment.


Within the same day, applications had been made to the UK Highways Agency for the permits required to move the biggest pieces of the production plant.


"Within a week of receiving the initial client call, all cargo was transported to port and loaded into the required containers, ready for export shipment. The cargo arrived at the final destination port in Izmir, Turkey, on time and under our client’s budget."

Daniel Morgan

Project Coordinator, HFS

Delivery

As Seen on TV

Our project manager quickly realised that the most economical solution was to relocate the heavy-duty, heat-treated packing timbers, which would eventually be used in the sea freight packing. A truck was dispatched the same day from Felixstowe to the factory site, so that the timbers were available to support the plant when it was loaded to our trucks.


Even split into two sections, each half of the main machine was still over 8 metres in length, nearly 5 metres wide and almost 4 metres high. Escort vehicles were required at both the front and rear of the convoy, which had to travel over 300 miles, partly through the small winding roads of the Snowdonia mountain range, to the Port of Felixstowe.


All of which was filmed by a TV production company following our trusted trucking partner for the award-winning documentary TV series – Supertruckers.


On arrival of the cargo at Felixstowe port, our personnel were on hand to witness and oversee the lifting and loading operation from truck to the flat rack shipping containers, as per the loading plan that we had already provided to the loaders.


Results

The Quickest and Safest Solution

The final piece of cargo to arrive was a large steel gantry section, to be loaded onto a flat rack container. On arrival it was discovered that the factory dismantlers had placed a large amount of loose steel pipework inside the open gantry frame.


Our project manager inspected the cargo in conjunction with the loaders and the shipping line appointed cargo surveyor, and were able to agree the quickest and safest resolution to this problem, was to decant all the loose pipework to a further 40ft dry container where it could be safely contained and with minimal additional costs to the client.


Within 1 week of receiving the initial client call, all cargo was transported to port and loaded into the required containers, ready for export shipment. The cargo arrived at the final destination port in Izmir, Turkey, on time and under our client’s budget.


We always take pride in our work, and a successfully completed job and a happy customer, makes it even more worthwhile.


Make HFS Your Logistics Partner

Which services are you interested in?
Logistic Services
Specialist Services










      We'll get back to you as soon as possible in regards to your enquiry. Hemisphere is committed to protecting and respecting your privacy. We will also occasionally contact you about products, services and content that we feel are both relevant and of interest to you. You can unsubscribe from these communications at any time or click the checkbox to the left if you prefer that we not contact you about how we can help. For more information please see our privacy policy.

      Related Case Studies

      SPEL Products

      Industry

      • Industrial
      "It was great to complete another successful storage tank shipment to the satisfaction of all involved. We look forward to being involved in further shipments relating to the 2022 World Cup both before and after, though of course, the only thing we really want to see coming home is the World Cup itself!"

      Dan Leach

      Projects Team Manager

      Liverpool Gas Scrubber

      Industry

      • Industrial
      "There were some challenges during the project, due to Sunday delivery days, police requirements and unforeseen road accidents, which meant quickly assessing and utilising an alternative route and calling in additional trucking escorts. Fortunately, we love thinking on our feet and solving problems as we go!"

      Daniel Morgan

      Project Coordinator

      Trelleborg

      Industry

      • Industrial
      "When you're playing a major part in a construction project to carry water between countries to resolve irrigation problems, you have to be on top of your game and ensure strict deadlines and specific project requirements are met."

      Louis Perrin